Social Housing Construction Status Report Q2 2020HousingSocial Housing Construction Status Report Q2 2020 The Construction Status Q2 2020 report shows that 8,529 homes were under construction at end Q2 2020; and some 3,160 homes had been approved and were about to go on site. The full programme listed in the report now includes...
-
A Commencement Notice (CN) is a notification to a Building Control Authority (BCA) that a person intends to carry out either works or a Material Change of Use to which the Building Regulations apply. The notice must be given to the authority not more than 28 days and not less...
-
A Commencement Notice (CN) is a notification to a Building Control Authority (BCA) that a person intends to carry out either works or a Material Change of Use to which the Building Regulations apply. The notice must be given to the authority not more than 28 days and not less...
-
A Commencement Notice (CN) is a notification to a Building Control Authority (BCA) that a person intends to carry out either works or a Material Change of Use to which the Building Regulations apply. The notice must be given to the authority not more than 28 days and not less...
-
A Commencement Notice (CN) is a notification to a Building Control Authority (BCA) that a person intends to carry out either works or a Material Change of Use to which the Building Regulations apply. The notice must be given to the authority not more than 28 days and not less...
-
A Commencement Notice (CN) is a notification to a Building Control Authority (BCA) that a person intends to carry out either works or a Material Change of Use to which the Building Regulations apply. The notice must be given to the authority not more than 28 days and not less...
-
A Commencement Notice (CN) is a notification to a Building Control Authority (BCA) that a person intends to carry out either works or a Material Change of Use to which the Building Regulations apply. The notice must be given to the authority not more than 28 days and not less...
-
Social Housing Construction Status Report Q4 2019HousingThe Construction Status Q4 report shows that 6,704 homes were under construction at end Q4 2019; and some 2,603 homes had been approved and were about to go on site. The full programme listed in the report now includes 1,916 schemes (or phases), delivering 26,015 homes – a...
-
Social Housing Construction Status Report Q3 2019HousingThe Construction Status Q3 report shows that 6,499 homes were under construction at end Q3 2019; and some 3,046 homes had been approved and were about to go on site. The full programme listed in the report now includes 1,645 schemes (or phases), delivering 22,721 homes – a...
-
Social Housing Construction Status Report Q2 2019HousingThe Construction Status Q2 report shows that 6,439 homes were under construction at end Q1 2019; and some 2,730 homes had been approved and were about to go on site. The full programme listed in the report now includes 1,559 schemes (or phases), delivering 22,139 homes – a...
-
Social Housing Construction Status Report Q4 2018HousingThe Construction Status Q4 report shows that 4,992 homes were under construction at end Q4 2018; and some 2,569 homes had been approved and were about to go on site. The full programme listed in the report now includes 1,299 schemes (or phases), delivering 19,134 homes – a...
-
Social Housing Construction Status Report Q3 2018HousingThis is an updated status list of social housing construction schemes that are advancing nationwide. This publication shows the picture at the end of Quarter 3 of 2018, where there are now over 17,500 new social homes being advanced by local authorities and approved housing...
-
Social Housing Construction Status Report Q2 2018HousingThis is an updated status list of social housing construction schemes that are advancing nationwide. This publication shows the picture at the end of Quarter 2 of 2018, where there are now over 16,300 new social homes being advanced by local authorities and approved housing...
-
Social Housing Construction Status Report Q1 2019HousingThe Construction Status Q1 report shows that 5,598 homes were under construction at end Q1 2019; and some 2,180 homes had been approved and were about to go on site. The full programme listed in the report now includes 1,416 schemes (or phases), delivering 20,324 homes – a...
-
HousingLocal Authorities, Approved Housing Bodies, the Housing Agency and the D/HPC&LG have been advancing a suite of social housing schemes, through a range of delivery mechanisms and programmes. This dataset provides a comprehensive list of these social housing schemes that are...
-
Social Housing Construction Status Report Q1 2017HousingThis is an updated status list of social housing construction schemes that are advancing nationwide. This publication shows the picture at the end of Quarter 1 of 2017, where there are now over 10,000 new social homes being advanced by local authorities and approved housing...
-
HousingThe index relates to costs ruling on the first day of each month. NATIONAL HOUSE CONSTRUCTION COST INDEX; Up until October 2006 it was known as the National House Building Index Oct...
-
Social Housing Construction Status Report Q1 2018HousingThis is an updated status list of social housing construction schemes that are advancing nationwide. This publication shows the picture at the end of Quarter 1 of 2018, where there are now almost 15,000 new social homes being advanced by local authorities and approved housing...
-
Social Housing Construction Projects - Status Report Q2 2017HousingAn updated status list of social housing construction schemes that are advancing nationwide, following on from the previous status list published in May, 2017.
-
Statistics based on analysis of Employment and Investment Incentive returns.